NO.61 A customer has a requirement to run a single instance Oracle Database VM on AHV that is driving over 250,000 IOPs.
Which AOS feature should be positioned to deliver the highest level of performance?

 
 
 
 

NO.62 A two-node ROBO cluster is configured with a witness VM.

What happens when Node A goes down?

 
 
 
 

NO.63 A customer intends to build out their VDI environment over a period of 18 months. They require a consistent user experience as their numbers grow. what element of the Nutanix WebScale architecture would a systems engineer discuss with them?

 
 
 
 

NO.64 Which two collection tool outputs can be imported into Nutanix Sizer? (Choose two)

 
 
 
 

NO.65 A prospect uses VMware, Oracle and Microsoft products for their critical operations. The prospect prefers an all-flash array because they have significantly invested in servers for their oracle environment to save on licensing costs.
Which feature should be discussed to address this objection?

 
 
 
 

NO.66 A prospective customer is concerned about the suitability and design of using Nutanix for an upcoming Avaya IP Office migration.
Which type of document should the systems engineer (SE) provide?

 
 
 
 

NO.67 An SE builds a Sizer scenario for SQL server running on Cisco C240 M4 servers.
Using only the Sizer BOM, which two actions can be performed? (Choose two)

 
 
 
 

NO.68 One of a prospective customer’s security analysts asks about Nutanix’s security functionality. The security analyst asks if Nutanix has any feature or capability that reduces the effort required to assess the security within the Nutanix infrastructure.
Which benefit does Nutanix SCMA provide to this prospect?

 
 
 
 

NO.69 A prospect’s business is growing 100% year over year. The prospect is interested in Nutanix for their main datacenter due to the alility to scale quickly and easily. They have three remote sites that will be refreshed within the next year. Each site needs to replicate to their many datacenter. The SE proposes the Nutanix NX line, and the prospect asks to utilize the Xpress line.
For which reason is the Xpress line the wrong choice? (Choose two)

 
 
 
 
 

NO.70 A customer has a 3-node cluster configured for RF2 with 100TB of raw disk space. The customer wants to enable Erasure Coding to gain additional usable space. What change will allow EC-X to be enabled?

 
 
 
 

NO.71 A customer needs to increase availiability in their Nutanix environment by enabling rack awareness. The current configuration consists of
* 1 RF2 cluster consisting of 7 identical NX-3170 1U nodes
* All storage efficiencies are disabled a single rack
* All nodes are in a single rack
Which two changes should the systems engineer propose to meet the customer requirements?(Choose two)

 
 
 
 

NO.72 A VP of Applications at a prospective customer is working to transform IT from a cost center to a business enabler. In order to address this initiative the VP has identified the following areas for improvement
* Increased time and expenses related to meeting business deliverables
* Missed market opportunity due to slow IT response time
* Shadow It increases risk of security breaches and brand damage
* Unplanned spend on public cloud services (AWS)
What two key benefits should the SE review to address the customer’s challenges? (Choose two)

 
 
 
 

NO.73 An SE needs to leverage Change Block Tracking when using Xtract to migrate VMs from ESXi to AHV.
Which two source VM requirements should the SE verify? (Choose two)

 
 
 
 

NO.74 Which two items are considered by Sizer when calculating the required cluster resources with only the Raw input workload type for a multi-VM workload? (Choose two)

 
 
 
 

NO.75 Refer to Exhibit:

An administrator logs in to Prism and sees the status shown in the exhibit within the Hardware Diagram section.
What should the administrator do?

 
 
 
 

NO.76 An administrator is managing multiple Windows and Linux VMs connected to Nutanix Volumes. The Linux VMs are experiencing intermittent connectivity issue. The Windows VMs do not experience the same issue. Which option should the administrator use to resolve this issue?

 
 
 
 

NO.77 During an initial discussion, a prospective customer indicates they are strongly conudenng VSAN for their HCI initiative.
The prospect’s workloads are mostly read-intensrve and they have over 1PB of archival data. The prospect expects to save on costs using storage efficiencies that their existing platform does not support Which two Nutanix differentiators should the systems engineer discuss? (Choose two)

 
 
 
 

NO.78 Refer to the exhibit.
***Exhibit is Missing***
Based on the Sizing scenario, what level of resiliency can be inferred about the configuration?

 
 
 
 

NO.79 AN SE determines that a POC is necessary to overcome competitive FUD in an opportunity with an Enterprise account evaluating several HCI solutions. The customer will evaluate three solutions in their datacenter simultaneously over the course of 4 days.
The customer schedules all necessary personnel to be available during this time.
Which two network planning items should the SE determine prior to allocation hardware for the POC? (Choose two)

 
 
 
 
 

NO.80 A prospective customer indicates a requirement to replicate data offsite for a production workload.
Which two questions should the systems engineer ask about the prospect’s requirement? (Choose two)

 
 
 
 

NO.81 A prospect has 8500GB of capacity provisioned for a non-production VMware cluster As part of migrating to Nutanix the prospedage to convert any thick provisioned disks to thin provisioned disks. Based on additional data, the total active working set for the duster has been determined to be 1TB.
When entering the Raw Input workload into Sizer, what is the minimum amount of HDD Capacity required for the workload?

 
 
 
 

NO.82 A prospects main goal are to replace their mainframe environment, cut their datacenter footprint, and improve disaster recovery for mission critical applications.
Which collection of documents should the SE use to show the prospect how Nutanix can help them reach their goals?

 
 
 
 

NO.83 A systems engineer (SE) is gathering requirements to size a hybrid cluster to replace a prospect’s existing IT test and development environment The prospective customer has indicated the cluster contains no business critical applications and has provided the aggregate vCPU and RAM requirements of the existing cluster.
Which two additional items does the SE require to size the cluster’ (Choose two.)

 
 
 
 

Get 2022 Updated Free Nutanix NCSE-Core Exam Questions and Answer: https://www.surepassexams.com/NCSE-Core-exam-bootcamp.html

         

Related Links: myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below