QUESTION 30
Additional Information

Further information on some resources who could be involved in the project:
Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project.
Director of Finance Division: She was transferred from the Information Technology Division 12 months ago. She is responsible for ensuring a cost-conscious approach is adopted in all operational and project activities across the Ministry of Food Hygiene.
Hardware Manager: Reports to the Director of Information Technology. He provides computer hardware to all business functions but has little awareness of the needs of his colleagues working in software.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running the Finance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry’s business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards.
Which 2 alternative actions apply to the proposed Senior User for this project?

 
 
 
 
 

QUESTION 31
The change control approach defines how products should be controlled and protected during the project. The accreditation of the ‘classroom-based training materials’ was planned to take place during stage 2. At the end of the stage, the configuration item record shows that the ‘classroom-based training materials’ have been accredited. However, the project manager decides to request an audit of the product as well.
Is this appropriate, and why?

 
 
 
 

QUESTION 32
Scenario
Product Summary
A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.
Product Breakdown Structure (contains errors)

Extract from Stage Plan for stage 3.
(All entries are true statements but may not be shown under the correct heading or in the correct document).

Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage.
Which 2 statements apply to the Plan prerequisites section?

 
 
 
 
 

QUESTION 33
It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO’s customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.
There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.
Which product should show that if anybody has any remaining resource costs to be charged to the project, they should ensure this is done by 10 November?

 
 
 
 

QUESTION 34
Which 2 statements should be recorded under the Costs heading?

 
 
 
 
 

QUESTION 35
If the Project Board are too busy to authorize all change requests themselves they can appoint?

 
 
 
 

QUESTION 36
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor’s calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.
Which 2 statements should be recorded under the Proximity heading?

 
 
 
 
 

QUESTION 37
Additional Information Product Description

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors) Introduction
1.This document defines the approach to be taken to achieve the required quality levels during the project.
2.The Project Board will have overall responsibility for the Quality Management Strategy.
3.Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure – Quality standards
4.The selected service provider will operate to industry standards for providing outsourced services.
5.MFH document standards will be used.
Records
6.A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7.Configuration Item Records will be maintained for each product to describe its status, version and variant.
8.Approval records for products that require them will be stored in the quality database. Roles and responsibilities
9.The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10.
Team Managers will provide details of quality checks that have been carried out.
11.
Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12.
The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Which is a correctly defined acceptance criterion for the service level agreement (SLA) with the selected service provider?

 
 
 
 

QUESTION 38
Towards the end of stage 2, the stage 3 plan is being prepared. This includes the work required to promote the new courses to other training companies. In addition to the current ways of marketing the courses, the Sales Director wants to advertise in trade magazines. The likely costs involved and the opportunities it may bring have been identified.
As part of the ‘update the project plan’ activity, what should the project manager be responsible for?

 
 
 
 

QUESTION 39
At the end of stage 2, the specialist ‘e-learning course’ supplier will be selected. As a result, it is decided that the quality management approach will not be created until the end of stage 2, to take into account this supplier’s standards and techniques.
Is this appropriate, and why?

 
 
 
 

QUESTION 40
Which of the following risk responses can be used for either an opportunity or a threat?

 
 
 
 

QUESTION 41
Who is responsible for the initial creation of the Configuration Item records?

 
 
 
 

QUESTION 42
Which of the following roles cannot be combined?

 
 
 
 

QUESTION 43
Which of the following activities could trigger the production of an exception plan?

 
 
 
 

QUESTION 44
Two weeks after starting work the Team Manager noticed that each completed product had exceeded its estimated effort by around 10%. If this trend continues the Work Package will exceed its agreed cost tolerance of 5%.
Which 2 actions should the Team Manager take in response to this situation?

 
 
 
 
 

QUESTION 45
There are four steps in the Risk Management procedure, what are they?

 
 
 
 

QUESTION 46
Which 2 statements should be recorded under the Costs heading?

 
 
 
 
 

QUESTION 47
Who is responsible for the initial creation of the Configuration Item records?

 
 
 
 

QUESTION 48
While deciding on how the work of the project should be approached the following were considered.
Which statement is appropriate for inclusion in the project approach heading in the Project Brief?

 
 
 

QUESTION 49
Which of the following is False?
A Successful project management team should.

 
 
 
 

QUESTION 50
Which of the following should NOT be included in the business case?

 
 
 
 

QUESTION 51
Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients’ work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor’s calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.
Which 2 statements should be recorded under either the Records or Reporting headings?

 
 
 
 
 

QUESTION 52
This question provides a number of changes which may or may not be required to the Extract from the
Communication Management Strategy provided in the additional information.
Which statement applies to the Timing of communication activities section?

 
 
 

Regular Free Updates PRINCE2Practitioner Dumps Real Exam Questions Test Engine: https://www.surepassexams.com/PRINCE2Practitioner-exam-bootcamp.html

         

Related Links: myportal.utt.edu.tt www.stes.tyc.edu.tw myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt www.stes.tyc.edu.tw

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below